Terminal & Concourse Misc. Upgrades Wall Wainscot Adjacent To Atrium Elevators
|
|
AATC |
$173,868.00
|
|
|
FC- 4979 - Concourse D Midpoint Advance Package
|
|
New South |
$4,416,496
|
|
|
FC-4862 - Consolidated Rental Car Facility (CONRAC) Operations and Maintenance
|
|
Meridian Management Corporation |
$10,333,336.00
|
|
|
FC- 4880 – C4 Special Systems
|
|
MC Dean |
$6,693,479.00
|
|
|
CPTC Vertical Transportation Upgrades; Phase I
|
|
AATC |
$2,800,000
|
8/18/09
|
|
FC-4925 Runway 10/28 Grading and Drainage Improvements
|
|
Archer Western |
$3,345,267.25
|
7/24/09
|
|
FC-3007000038F - Parking Deck Joint Seal Project
|
|
GSC Atlanta/Civic Works |
$4 million
|
6/01/09
|
|
FC-3007000038C - Misc. Built-up Roof & Single Ply Roof Repairs
|
|
New South/Circle D |
$1,099,049
|
4/08/09
|
|
FC- 4162 Terminal Restroom Upgrades
|
|
New South Company, Inc.
|
$2,082,400.00
|
Contact Information:
New South Construction
1132 West Peachtree Street
Atlanta, GA 30309
(404) 443-4000(p)
(404) 443-4100 (f)
|
|
|
|
CPTC Roof Replacement Concourse “D”
|
|
AATC
|
$4,109,407
|
Contact Information:
AATC – New South / Holder / Bryson
P.O. Box 4517
Atlanta, GA 30320 (404) 530-2100
|
|
|
|
FC- 4097- Airport Roadway Repair & Maintenance, Airport Capital Roadway Improvements
& Additions
|
|
Archer Western/Capital
|
C.W. Matthews - $2,173,390.53
|
Contact Information:
Archer Western Contractors, Ltd.
3715 Northside Parkway, NW
Building 100, Suite 550
Atlanta, Georgia 30327
(404) 495-8700 (p)
(404) 495-8701 (f)
|
|
|
|
FC-3007000038 H-JAIA Managing General Contractors(On Call):
|
|
|
|
FC-3007000038A(H-JAIA Managing General Contractors)
|
On-call Services
|
07/06/08
|
Contact Information:
Archer Western Contractors, Ltd.
3715 Northside Parkway, NW
Building 100, Suite 550
Atlanta, Georgia 30327
(404) 495-8700 (p)
(404) 495-8701 (f)
|
|
|
|
FC-3007000038B(H-JAIA Managing General Contractors)
|
On-call Services
|
08/18/08
|
Contact Information:
Bryson/Precision 2K
Contact Name: Steven Barnes
2847 Main StreetM
East Point, GA 30344
(404) 762-1000 (p)
|
|
|
|
FC-3007000038C(H-JAIA Managing General Contractors)
|
On-call Services
|
06/05/08
|
Contact Information:
New South Construction
1132 West Peachtree Street
Atlanta, GA 30309
(404) 443-4000 (p)
(404) 443-4100 (f)
|
|
|
|
FC-3007000038D(H-JAIA Managing General Contractors)
|
On-call Services
|
06/05/08
|
Contact Information:
Turner/Davis
Contact Name: John Litchenwalter
3424 Peachtree Street
Atlanta, GA 30309
(404) 295-1825 (p)
|
|
|
|
FC-3007000038E(H-JAIA Managing General Contractors)
|
On-call Services
|
07/02/08
|
Contact Information:
CW Matthews Co. Inc.
P.O. Drawer 970
Marietta, GA 30061
(770) 422-7520 (p)
(770) 422-1068 (f)
|
|
|
|
FC-300700000038C - Safety Command and Control Center |
|
New South/Circle D
|
|
|
FC-30070000037B Interfaith Chapel Relocation |
|
Biosphere International
|
$962,889.50
|
|
FC- 4556 A& B Structural Testing & Special Inspections |
|
ATC Associates Inc.
|
$800,000
|
|
Terrocon Consultants, Inc
|
$400,000
|
|
FC-3007000049 - Fire Station # 24 Demolition and Re-Construction |
|
The Lions Group Inc./Key Engineering, JV
|
$6,043,620.00
|
|
FC-3007000002– Comprehensive Environmental Services at H-JAIA
|
|
Metcalf & Eddy, Inc., and Tri-Tech Associates, Inc., JV- (ESAF)
|
|
FC-3007000003 – Fuel Main – Maintenance/Upgrade/Improvements
|
|
Player & Company |
$2,437,525
|
|
FC-3007000021– Tech Campus Repairs - 2007 |
|
Circle D Enterprises |
$1,283,514.00 |
|
FC-3007000029 - Park Ride Lot A Office Replacement
|
|
Awarded to JaTech & Associates, Inc. |
$590,100.00 |
|
FC-3007000023 – Extension of Taxiway L and 27R RSA and Taxiway M Pavement Replacement
|
|
Awarded to Archer Western / APAC, JV
|
$42,347,254.26 |
|
FC-3007000021- Tech Campus Repairs - 2007 |
|
Circle D Enterprises, LLC. |
$1,283,514.00 |
|
|
|
FC-6006007929 Architectural Engineering Design Support Services at H-JAIA:
|
|
FC-6006007929-A |
Hartsfield Support Service Team
|
|
FC-6006007929-B |
Hartsfield-Jackson Aviation Design Collaboration
|
|
FC-6006007929-C |
Aviation Infrastructure Solutions
|
|
FC-6006007929-D |
Hartsfield-Jackson Transportation Group
|
|
FC-6006007929-E |
Ascend, LLC
|
|
Project #
FC - 6005007882 - Noise Insulation Program |
|
THC, Inc. |
$10,000,000.00
|
|
Project #
FC-3006007998 – Airfield Pavement Repairs / Maintenance 2007 |
|
Precision 2000 |
$1,851,720.00
|
|
Project # FC# 3007000006 – CONRAC Access Roadway
|
|
GSC Atlanta/ Civil Works
|
$30,428,000
|
|
PROJECT# FC-3006007997 - Mercury Air Cargo Demolition
|
|
Kissberg Construction, Inc. |
$357,170.00
|
|
PROJECT# FC-3006007963 –H-JAIA Apron Pavement Replacement Ramps
2, 3, 5 |
|
Archer Western Construction
|
$16,015,991.15
|
|
|
FC-3006007946 – Airline Employee Parking Relocation, Phase 1
|
|
DynaElectric Company |
$2,448,610.65
|
|
|
FC-3006007966 – Concourse E Unit Substation 10 & South Airfield
Lighting Vault Generator |
|
Cleveland Electric |
$2,725,006.00
|
|
|
PROJECT# FC-3006007981 – Taxi Cab Service Building Roof Recovery
at H-JAIA |
|
NTEC Systems, LLC
|
|
|
|
PROJECT# FC-3006007985 – Concessions Office
Remodel 06 |
|
Awarded to Kissberg Construction
|
$450,000
|
|
|
PROJECT# FC-3006007975 – N. Cargo Building Roof Replacement &
Repairs at H-JAIA
|
|
Campbell Roofing
|
$2,578,856.00
|
02/2007
|
|
PROJECT FC 3005007894 - Runway Safety Areas 26R/9L/9R
|
|
Paramount Construction |
$3,288,860.00
|
|
|
PROJECT FC 3006007917 Runway 10/28 NLVR
|
|
Precision 2000 |
$2,894,259.00
|
|
|
PROJECT FC 3005007891 - Fire Station No. 24 Renovations and Improvements |
|
New South Construction/Circle D |
$4,145,000.00
|
|
|
PROJECT FC 3005007892 - Airfield Recycled Materials Site Management |
|
Stephens MDS, LP/The Lions Group, J.V.
|
$53,291,736.79
|
|
|
PROJECT FC 3005007893 - Runway 8R/26L Pavement Replacement |
|
GSC Atlanta, Inc.
|
$91,490,317.00
|
|
|
CPTC Cosmetic Upgrades |
|
AATC |
$33,141,987.00
|
N/A
|
|
Computer-Aided Dispatch Implementation at H-JAIA |
|
INFAX |
$3,387,740.00
|
N/A
|
|
Project FC3005007867 Taxiway V (8R End Around Taxiway) |
|
Archer Western
|
$37,696,492.78
|
12/05
|
|
Project # 7692-04 CONRAC Automatic People Mover System Fixed
Facility Design/Build Team and APM System Supplier |
|
Archer Western/Capital Contracting JV |
$170,501,627
|
11/1/05
|
|
PROJECT #
FC-7689-04 CONSTRUCTION MANAGER AT RISK - Maynard H. Jackson
Jr. International Terminal Building |
|
Holder, Manhattan, Moody and Hunt (HMMH) |
-
|
11/04
|
|
PROJECT #
3004007808 CONSTRUCTION MANAGER AT RISK CONSOLIDATED RENTAL CAR FACILITY (CONRAC) |
Austin Commercial/PRAD Group JV
|
-
|
10/11/05
|
|
02-R-0506, AATC REIMBURSABLE AGREEMENT –
CPTC Fire Alarm And Sprinkler Systems Lighting System Replace Dry Standpipe
Fire System Upgrades, HVAC System Upgrades And VFD Installation
|
|
AATC – New South / Holder / Bryson
|
$65,359,670
|
12/9/02
|
|
FC-7227-00, CONCOURSE E PHASE 2 MOVING WALKWAYS
|
|
Malone Construction
|
$3,302,054
|
3/25/04
|
|
FC-7687-04 SECURITY ACCESS CONTROL SYSTEM
|
|
M.C. Dean
|
$13,996,597.91
|
3/14/05
|
|
PROJECT # 3004007830 SURFACE MOVEMENT GUIDANCE
CONTROL SYSTEM |
|
Brooks-Berry-Haynie/Dixie Electric Company
|
$14,802,880.00
|
5/25/05
|
|
PROJECT # FC-3004007816, FIRE STATION NO. 35
- RENOVATIONS AND IMPROVEMENTS AIP NO. 3-13-0008-61
|
|
Paramount Construction/font> |
$1,684,100.00
|
6/2/05
|
|
PROJECT # FC-XXA12-999 Terminal Cosmetics Concourse A, B, C,
& D Transportation Mall and Concourse "T" HVAC Upgrades through AATC
|
|
AATC |
$6.84 million
|
N/A
|